This project involves the installation and tailoring of curtains for a client’s home. The project will be completed in seven days.

Tasks:

  • Day 1: Meet with the client to discuss their needs and preferences. Take measurements of the windows.
  • Day 2: Select the fabric and hardware for the curtains.
  • Day 3: Order the fabric and hardware.
  • Day 4: Receive the fabric and hardware.
  • Day 5: Cut and sew the curtains.
  • Day 6: Install the curtains.
  • Day 7: Clean up and remove any debris.

Materials:

  • Fabric
  • Hardware
  • Tools

Timeline:

The project will be completed in seven days.

Budget:

The budget for the project is $1,000.

Contingency Plans:

  • If the fabric or hardware is not available on time, the project may be delayed.
  • If there are any unforeseen problems with the installation, the project may take longer to complete.

Communication Plan:

The project manager will communicate with the client on a regular basis to keep them updated on the progress of the project.

Approvals:

The client will need to approve the fabric, hardware, and installation plan before the project can begin.

Acceptance Criteria:

The project will be considered complete when the curtains have been installed and the client is satisfied with the results.